2026-02-12
Wall Street Journal
5 related
Meta's auditor Ernst & Young raised a red flag over the financial engineering Meta used to keep its $27B Hyperion data center project off its balance sheet
Meta Platforms' latest annual report contained an unusual, cautionary note for investors. — The tech giant's auditor …
2025-12-21
Sherwood News
1 related
A look at Meta's 2GW Hyperion data center in Louisiana, with the first phase opening in 2028; an analysis shows sales tax breaks on GPUs could total $3.3B+
2025-12-20
Sherwood News
2 related
A look at Meta's 2GW Hyperion data center in Louisiana, with the first phase opening in 2028; an analysis shows sales tax breaks on GPUs could total $3.3B+
$10 billion of investment. Code names to disguise projects and companies. Mixed opinions. Skyrocketing property values.
2025-10-22
Reuters
8 related
Meta forms a JV with Blue Owl to fund the $27B, 2GW Hyperion data center in Louisiana, its largest ever private capital deal; Meta will retain a ~20% equity
Meta (META.O) has struck a $27 billion financing deal with Blue Owl Capital to fund its biggest data center project globally …
2025-10-17
Bloomberg
5 related
Sources: Meta is set to seal an almost $30B financing package for its Hyperion data center in Richland Parish, Louisiana, with Meta retaining 20% ownership
Bloomberg :